CAPINHA DAM

PURPOSE - Water supply / Irrigation
LOCATION GENERAL FEATURES
District - Castelo Branco
Municipality - Fundão
Site - Capinha
River Basin - Tejo
River - Poldras river
Promoting entity - INAG
Owner (RSB) - INAG
Engineering by - COBA
Construction by - Tecnopul
Project year - 1979
Year of completion - 1981
HYDROLOGY RESERVOIR
River basin area - 6,3 km2
Mean annual rainfall - 1058 mm
Mean annual runoff - 3530 x 1000 m3
Flood runoff - 32,5 m3/s
Return period - 1000 years
Reservoir area - 97 x 1000m2
Gross capacity - 522 x 1000m3
Effective storage - 340 x 1000m3
Dead storage - 182 x 1000m3
Normal water level (NWL) - 502,5 m
Maximum flood level (MFL) - 503,31 m
Minimum operating level - 498 m
DAM
Earthfill - Homogeneous embankment
Height above foundation - 18 m
Height above streambed - 16 m
Crest elevation - 505 m
Crest length - 231 m
Crest width - 7 m
Foundation - Granite
Volume of dam body - 82 x 1000 m3
SPILLWAY BOTTOM OUTLET
Location - Left bank
Control type - Uncontrolled
Spillway type - Shaft spillway
Sill elevation - 502,5 m
Sill length - 18,5 m
Maximum discharge - 26,3 m3/s
Energy dissipation - Hydraulic jump
Location - Left bank
Type - Conduit under the embankment
Section - d 0,60 m
Maximum discharge - 2,3 m3/s
Upstream control - Fixed roller gate
Downstream control - Butterfly valve
Energy dissipation - Hydrauilic jump